|
APM
utilizes a revolutionary new approach to planning, scheduling, costing and tracking called Total Project Control. The TPC method, the subject of a new book published in May 1999
by John Wiley & Sons, allows both an individual project, and an organization's entire project portfolio, to be planned and tracked on the basis of revenues and profitability.By enhancing the
methods of "traditional" project management, and introducing new techniques, concepts, and data items, TPC provides quantified profitability data in support of such management decisions as:
- Product design, scheduling, and budgeting.
- Setting of project deadlines.
- Scope adjustments in response to slippage or market changes.
- Project priorities based on maximized portfolio value.
- Staff "rightsizing" based on dollarized cost of bottlenecks.
- R&D budgets justified through NPV and risk management.
- Setting of corporate quality standards.
- Evaluation of project management performance.
It is a truism of total quality management that what can be measured can also be improved. The ultimate goal of TPC is a corporate culture in which each project team member, every project manager,
and every executive is working toward maximized profitability, not just for the individual project but across the entire corporate portfolio.
Take, for example, the case of the senior manager with the project portfolio shown below:
Proj. Name |
Expected Value (000) |
As Of |
Current Comp Date |
% Loss per week late |
% Gain per week early |
Cost ETC |
Simple DIPP |
A |
$1,000 |
Aug 1 |
Aug 1 |
5% |
5% |
$200 |
5.0 |
B |
$2,000 |
Oct 1 |
Oct 1 |
10% |
5% |
$1,000 |
2.0 |
C |
$5,000 |
Nov 25 |
Nov 25 |
20% |
2% |
$2,000 |
2.5 |
D |
$10,000 |
Jan 30 |
Jan 30 |
10% |
5% |
$3,000 |
3.3 |
Total Portfolio: |
Expected Value: $18,000 |
Cost ETC: $6,200 |
Expected Net: $11,800 |
Simple DIPP: 2.9 |
The data above are a subset of the standard data provided by the TPC methodology. With
these, the manager can forecast profits and revenues, measure the impact of resource shortages or other delays, and even weigh hiring or outsourcing decisions on the basis of profitability impact.
But what happens when the following addition to the project portfolio is suggested?
Proj. Name |
Expected Value (000) |
As Of |
Current Comp Date |
% Loss per week late |
% Gain per week early |
Cost ETC |
Simple DIPP |
E |
$12,000 |
Feb 10 |
- |
20% |
5% |
$3,000 |
4.0 |
Without access to TPC data, the manager will probably take on what seems like a profitable
new project. And when profits decrease, it will be blamed on bad luck, or poor project management, rather than the simple lack of adequate data, as shown on the next page.
TPC mandates that project data must be analyzed across the entire portfolio. And, unfortunately, when Project E is added to the portfolio, its impact on the organization's
limited resource pool delays all the other projects, with the following result:
Proj. Name |
Expected Value (000) |
As Of |
Current Comp Date |
% Loss per week late |
% Gain per week early |
New Exp. Value |
Cost ETC |
Simple DIPP |
E |
$12,000 |
Feb 10 |
Feb 10 |
20% |
5% |
$12,000 |
$3,000 |
4.0 |
A |
$1,000 |
Aug 1 |
Aug 29 |
5% |
5% |
$800 |
$200 |
4.0 |
B |
$2,000 |
Oct 1 |
Oct 29 |
10% |
5% |
$1,200 |
$1,000 |
1.2 |
C |
$5,000 |
Nov 25 |
Dec 16 |
20% |
2% |
$2,000 |
$2,000 |
1.0 |
D |
$10,000 |
Jan 30 |
Mar 13 |
10% |
5% |
$4,000 |
$3,000 |
1.3 |
Total Portfolio: |
Expected Value: $20,000 (+ $2,000) |
Cost ETC: $9,200 (+ $3,000) |
Expected Net: $10,800 (- $1,000) |
Simple DIPP: 2.2 (- 0.7) |
Despite the fact that the new project is very profitable, the TPC data clearly show that the
organization's resource limitations will drive profits down, not up, unless changes are made to the plans for the existing projects.
Fortunately, other TPC data are available at the level of the individual project. These data can help point the project managers in the right direction, targeting the optimum activities
for shortening durations, adding resources, or trimming work scope. Again, these are data that traditional project management methods and software do not provide. Most project
managers would be hard pressed to determine which activity in the network logic diagram on the next page is causing the most delay.
But TPC's DRAG calculation (above) shows that Activity B is adding 18 days to the project's
critical path, far more than any other task. Can something be done to remedy this? TPC's Net Value-added and CLUB data items help the project managers optimize each project's
plan. Then senior management's multiproject data suggests a new portfolio profile:
Proj. Name |
Expected Value (000) |
As Of |
Current Comp Date |
% Loss per week late |
% Gain per week early |
New Exp. Value |
Cost ETC |
Simple DIPP |
E |
$12,000 |
Feb 10 |
Jan 13 |
20% |
5% |
$14,400 |
$3,500 |
4.1 |
A |
$1,000 |
Aug 1 |
Sep 12 |
5% |
5% |
$700 |
$200 |
3.5 |
B |
$2,000 |
Oct 1 |
Oct 15 |
10% |
5% |
$1,600 |
$1,000 |
1.6 |
C |
$5,000 |
Nov 25 |
Nov 25 |
20% |
2% |
$5,000 |
$2,000 |
2.5 |
D |
$10,000 |
Jan 30 |
Feb 27 |
10% |
5% |
$8,000 |
$4,000 |
2.0 |
Total Portfolio: |
Expected Value: $29,700 (+ $9,700) |
Cost ETC: $10,700 (+ $1,500) |
Expected Net: $19,000 (+ $8,200) |
Simple DIPP: 2.8 (+ 0.6) |
The above table shows that by increasing the budgets for Projects D and E by a total of
$1.5 million, a multiproject schedule can be implemented that can generate $8.2 million in additional profits. Would this be the optimum profile? Is the cash flow available to increase
expenditures in such a way? Such questions can only be answered through further analysis. But only TPC provides the data for such analysis, across work scope, schedule
and cost, as well as across all projects in the organizational portfolio. Without such data, even the questions are unknowable. |