|
AGENDA FOR A PROJECT POSTMORTEM
(To be conducted at project completion.)
- Original Project Business Case
- Original project business case.
- Original project customer value drivers (preferably monetized).
- Original project internal business value drivers (preferably monetized).
- Original bases of estimates.
- Project Risk/Opportunity Metrics
- List of risk/opportunity factors and the disposition of each.
- Original level-of-confidence in cost and schedule of baseline plan (80-20?).
- Estimate of likely number of ECPs.
- Actual number of ECPs.
- Project Technical Analysis
- Expected technical risks
- Emergent technical risks
- Disposition of risks
- Project Actual Value vs. Estimates Analysis
- Original estimate of project value in dollars.
- Present estimate of project value in dollars.
- Variances in product or project scope, or schedule, that resulted in the total variance.
- Specific decisions, ECPs, or other causes, of such project value variances.
- Current estimated DIPP divided by originally estimated DIPP (DBI).
- Project Actual Schedule vs. Estimates Analysis
- Project SPI on original baseline completion date.
- Project SPIs of each functional area on original baseline completion date.
- The original (planned baseline) critical path (CP).
- The As Built Critical Path (ABCP).
- Position of finish date in original level-of-confidence estimate (55-45?).
- Specific decisions, ECPs, or other causes, which caused the differences between the original CP and the ABCP.
- Functional area with the most DRAG and DRAG Cost on the original CP.
- Functional area with the most DRAG and DRAG Cost on the ABCP.
- Ten tasks with the most DRAG and DRAG Cost on the original CP.
- Ten tasks with the most DRAG and DRAG Cost on the ABCP.
- Project Actual Resource Availability vs. Estimates Analysis
- Ten specific resource limitations expected to cause the most DRAG on the original CP.
- Ten specific resource limitations which actually caused the most DRAG on the ABCP.
- Project Actual Cost vs. Estimates Analysis
- Actual cost of project cost in dollars.
- Original estimate of project cost in dollars.
- Final project CPI.
- Final project CPIs of each functional area.
- Position of actual cost in original level-of-confidence estimate (50-50?).
- Specific decisions, ECPs, or other causes, that added up to the total cost variance.
- Decisions, or other causes, of such cost variances.
- Itemized list of valuable lessons for future projects.
- Date in the future at which actual value generated by this project can be better assessed.
|