Exercise 2 - DRAG Analysis In A Finish-To-Start Network

Now the really important stuff! In Exercise 1:

  1. How much time is each activity adding to the project duration? Compute the DRAG of: A = , C = , F = , I = , L = .


  2. If the budget for each activity is $1,000 per unit of activity duration, and the project profit will increase by $5,000 for each unit of project duration less than 65, what is the true cost of doing each activity?