| Exercise 1 - Network Logic Diagram Finish-To-Start Traditional Analysis |
Perform the forward and backward passes on the network below to get their
earliest and latest starts and finishes. Then:
- List all the critical path activities:
- List all the non-critical path activities, with each of their total float amounts:
- Which have free float and how much?
|